The performance actually being achieved even though the authorized hours may suggest that the performance should be higher. The difference between demonstrated performance and authorized performance is known as the Load Factor (see Load Factor) and is used to calculate the Planned Demonstrated Performance. Future plans should not be produced with anything other than the demonstrated performance, if they are they are a wish list.